Construction progress

The following photos have been collected to reflect the construction progress of the US 17 Bypass. Please refer to this site regularly for updated progress photos. Please click on individual photos to view a larger image.

Work Ongoing During October 2002


Looking north from end bent #1 across US 421. Shows footings and stems on bents # 2, 3, and 4.

Looking south from bent #54 at decking forms and girder setting gantry.

Looking north from bent #54 at decking forms.

Looking north from bent #56 at deck section ready to be poured. Shows “Bidwell” screed.

Looking south from end bent #2 at work bridge and rail. Stagnamic test forms shown on bridge deck.

Looking south at bent #42. Shows the 3,200 cubic yard footer and the reinforcing steer for the 1st section of pier.

Looking across top of bent #42 footer. Show height of reinforcing steel for 1st section of pier.
 
Looking north from bent #42.