Construction progress

The following photos have been collected to reflect the construction progress of the US 17 Bypass. Please refer to this site regularly for updated progress photos. Please click on individual photos to view a larger image.

Work Ongoing During January 2002

Bent # 43. Piles in place in work template on north edge of Rat Island.
Looking back north from Bent #43 across North Channel of the N.E. Cape Fear River.
Bent #47. Piles with caps for work platform in North Channel of the N.E. Cape Fear River.
Bent #49. Piles for work platform in place.
Bent #51. Structural steel platform of work area between footing.
Reinforcing steel cage for drilled pier ready to be set in Bent #52.
Bent #54. Drilled piers poured. Work platform removed from around piers.
5-yard bucket of concrete being delivered to Bent #56. Pouring LT footing.
Bent #60. Cap ready to be cast.