Construction progress

The following photos have been collected to reflect the construction progress of the US 17 Bypass. Please refer to this site regularly for updated progress photos. Please click on individual photos to view a larger image.

Work Ongoing During February 2002

Overall view from end bent #2 - Cap on Bent #60 has been poured. Pouring cap of bent #59.
Shows pile template for end bent #2.
Concrete being pumped to bent #59 cap.
Shows second cap form being built to increase production.
Looking back from bent #55. Shows three bents where columns have been poured.
Preparing footing for bent #55.
Footings on bent #54 have been poured. Contractor is leap frogging bents.
Drilled piers have been poured on bent #52.
Technician monitoring the Shaft Inspection Device (SID) test on bent #51
The SID equipment being used on bent #51.
Drilling piers on bent #50.
Continuing to construct work bridge at bent #39.


PBS&J Privacy Policy and Legal Disclaimer
 






In the News

Wilington Star (11/4/01)