Construction progress

The following photos have been collected to reflect the construction progress of the US 17 Bypass. Please refer to this site regularly for updated progress photos. Please click on individual photos to view a larger image.

Work Ongoing During August 2002


Work bridge south of NE Cape Fear River. 8 spans erected.

Jack hammering excess concrete from drilled shafts in footing 42. All shafts complete on north side of river.

Overall view of shafts in bent #42 footing. This footer requires 3,200 cubic meters of concrete.

Second section of stem on bent #46 being readied to be poured about 60 feet high.

Overall view of work looking north from bent #47.

Overall view of work looking south from bent #48.

Setting girder in span #56.

Shows reinforcing steel and forming of deck from span #61 looking south.

Steel piles driven for bent #3 footing.